18/09/25: Another challenging construction project is nearing completion: As the general planner (#EPCM) as well as the MEP and cleanroom designer, we supported the construction of JENOPTIK’s new high-tech fab in #Dresden, from the initial planning stage to the commissioning of the production facilities.

Our contribution to equipment hook-up and commissioning included:

    • Support in planning hook-up layouts
    • Creation of toolbooks (including equipment cards and P&ID diagrams)
    • Planning of tool foundations
    • Continuous support throughout all project phases
    • Search for and coordination of local partners for media such as gases, chemicals, ultra-pure water, wastewater, cooling water, exhaust air, and electrical/ I&C
    • On-site coordination at the construction site
    • We would like to thank everyone involved in the project for their trusting cooperation and look forward to the next steps together.